Chickasaw County approves Iowa DOT agreements for U‑56 overlay and bridge projects
Summary
The board approved a federal Surface Transportation Block Grant agreement for a concrete overlay on U‑56 (federal share described as $1.81 million or 80% of construction cost) and approved a bridge deck overlay agreement estimated at about $232,000; short, scheduled road and bridge closures were discussed.
Get email alerts on the Transportation topic
No spam. Unsubscribe anytime.
Chickasaw County supervisors on May 10 approved two Iowa DOT agreements for road and bridge work: a Surface Transportation Block Grant (STP) agreement for a concrete overlay on U‑56 and a bridge deck overlay agreement for Bridge 1810.
The county engineer described the U‑56 concrete overlay project and presented the federal aid agreement (STP‑SD‑CO19126‑5E). The engineer summarized the federal contribution as "$1,810,000 or 80% of project construction cost, whichever is less" and recommended signing the county signature block. The board approved the agreement.
On bridge work, the engineer presented a county highway bridge project (BHS CO 19127‑63‑19) for Bridge 1810, a deck‑overlay project scheduled for the following year with an estimated cost of about $232,000 to be paid from the county highway bridge program. The board approved that agreement as well.
The engineer also reviewed a separate set of short closures and overlay repairs: a contracted quote of $49,088.77 was approved for three small bridge overlay repairs (Bridge 3090, Bridge 1620 and a bridge south of Bassett) with each closure expected to be under 48 hours and not requiring a detour. The engineer explained timing, access constraints and the need to coordinate with DOT on utility relocations and wetlands at other larger projects.
Why it matters: these approvals move forward federally funded and county bridge projects that affect travel and local maintenance schedules. The U‑56 pipeline overlay is largely federally supported but will require local administration; the bridge work includes unavoidable short closures that the engineer said would be limited to short windows and scheduled for low‑traffic periods.
What’s next: staff will execute the DOT agreements with county signatures and coordinate contractor scheduling and public notifications for planned closures.