Residents press Beaver County commissioners over proposed hyperscale data centers; officials cite limited permitting authority
Summary
At a May 20 work session, residents urged Beaver County commissioners to oppose proposed hyperscale data centers, citing health, noise, environmental and property-value concerns. County officials and the solicitor said local zoning and state permits determine siting and urged municipalities to adopt protective ordinances.
Get email alerts on the Data Centers topic
No spam. Unsubscribe anytime.
Residents pressed Beaver County commissioners at a May 20 work session to oppose proposed hyperscale data centers and to protect local air, water and property values.
"A data center is not for the benefit of all the people or the environment," said Cynthia L. Evans of Big Beaver Borough during the meeting's public-comment period, citing Article I, Section 27 of the Pennsylvania Constitution and warning that one proposal she described as "300 football fields" would bring continuous noise, diesel-generator testing and property-value declines.
The meeting drew additional testimony from Kendra Grosskost of Midland, who said Bitcoin-mining operations near her home have produced vibration and new or worsening health symptoms for family members and argued there has not been an independent human-impact or environmental analysis for so-called Project Phoenix. "There's never been a human impact analysis by a trusted third party for this," she said.
Commissioners and the county solicitor responded by describing the limits of county authority. County Solicitor (name not provided in transcript) told the room that when a developer applies to a municipality, that local government—not the county—typically reviews zoning and conditional-permit requirements. "If a data center comes in in one of those areas that's zoned to allow it and they meet all the conditions that otherwise is required in that ordinance, you have to vote that by law to approve it or else the data center will turn around and say you're not properly applying your zoning ordinance and we'll take it to court," the solicitor said, urging municipalities to adopt targeted zoning or conditional-use standards (sound, lighting, traffic) to limit local impacts where allowed by law.
Some commissioners said they support the Shippingport project because the developer presented a plan, the site is a brownfield and the project met the criteria they reviewed. "It's on a brownfield site ... it's being redeveloped," one commissioner said, adding that the county toured a similar facility and found noise to be minimal at that site.
Residents countered that municipal hearings and posted materials do not reach everyone and that public notice and engagement have been insufficient in some boroughs. Speakers urged the county to share contacts for third-party experts and to alert municipalities to model ordinances that can set enforceable conditions if a data center application comes forward.
The work session produced no formal vote or binding county-level action. Commissioners directed staff to follow up with contacts and promised to share information on model ordinances and monitoring options; the meeting then moved to an executive session to discuss personnel and litigation matters.
Ending: The discussion left unresolved technical and scientific claims raised by residents (for example, alleged health effects, generator testing schedules and property-value impacts). County officials reiterated that municipal zoning and the Commonwealth permit process will determine siting and that residents who want locally tailored limits should pursue ordinance changes with their municipal councils. The county indicated staff would follow up with interested residents and provide contact information for consultants mentioned during the meeting.