Village engineer says Park 90 gas-main work is complete; contractor to resume next week

Village of Machesney Park Board of Trustees · May 18, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Village engineer Nick Arps reported that Nycor Gas has completed lowering a gas main at the Park 90 site and that contractor Entrack is expected to return mid- to late next week to continue on-site work.

Village Engineer Nick Arps provided a construction update on the Park 90 project at the May board meeting, reporting that a gas-main relocation is finished and that site work will resume shortly.

Arps said, "Nycor Gas has completed the lowering of their gas main, so we expect Entrack to return to the site mid to late next week to continue that work on the ride in, ride out." The update described progress but included no schedule changes, cost figures or permitting issues.

The engineer's brief report was given as part of routine administrative updates; no formal board action was taken on the Park 90 project during the meeting. The village will provide further updates through staff reports as construction progresses.