Summary

A property owner told the council the city's sewer main collapsed on Feb. 2, 2026, forcing tenants to evacuate and the owner to pay $13,509.24 to repair the line; he asked the council to reimburse the cost and consider waiving reconnection fees under city ordinance if reconnection is ordered.

John Corson, a property owner in Ishpeming, urged the City Council to reimburse him $13,509.24 for an emergency repair to a collapsed sewer main that serves four houses on his block.

Corson told the council the main collapsed on Feb. 2, 2026, flooding his building with raw sewage, forcing tenants to evacuate and compelling him to hire an excavator to fix the break. He said city crews were notified several times and that a city foreman initially promised assistance that was later withdrawn. Corson said the city did not act until Feb. 13, after the state's environmental office intervened, and that his contractor completed the repair and backfill.

Corson said city records show the pipe dates to the 1930s, connects to a city sanitary manhole and was documented in a 1985 inspector's report as the "alley sewer" serving all four properties. He argued that Michigan law requires a formal legal process to abandon a drain and said the city has produced no paperwork showing it abandoned the main; he therefore said the pipe remains city infrastructure.

"Either it was an attempted abandonment, not followed by state law, or it was never abandoned, meaning they still own it," Corson said. He asked the council to do two things: authorize reimbursement of the $13,509.24 he paid to repair the city pipe, and, if reconnection to Euclid Street is ordered, invoke Ordinance 12-204 subsection 3 to waive reconnection costs for all four property owners on the block because the problem originated in public infrastructure.

Corson said he was not seeking a handout but rather a resolution in good faith after tenants were evacuated and his property suffered sewage damage.

Council did not take immediate action during public comment. City staff later discussed sewer-line repairs in the finance presentation and noted related sewer-fund expenditures; any formal request for reimbursement would require follow-up by staff and likely a council agenda item for action.