Oley Valley board approves rooftop solar on flat roofs, rejects slanted-roof installation
Summary
The Oley Valley School Board voted to install solar panels on flat roof surfaces at the elementary, middle and high schools but rejected placing panels on slanted roofs at the elementary school; board members debated a roughly $10,000 annual trade-off tied to including slanted roofs.
Get email alerts on the Solar Energy topic
No spam. Unsubscribe anytime.
The Oley Valley School Board on May 20 approved installing rooftop solar panels on flat roof surfaces across district schools while voting down a proposal to include slanted roofs at the elementary school.
The board discussed five related motions brought by the property and transportation committee. Members tabled a proposal for a ground-mounted array and then rejected Motion 1, which would have placed panels on slanted roofs as part of a larger district package. The board then approved Motion 5 to place panels on the elementary school flat roof surfaces only, and approved Motions 2 and 3 to install panels on the flat roofs of the middle and high schools.
The district estimated the full package using all roofs could generate roughly $101,000 in annual savings or income, while excluding the slanted roofs would yield about $90,800 — a difference of approximately $10,000 per year that drove much of the debate.
Board member Klein argued for the financial case, urging the board not to forgo the additional revenue. "I think it's irresponsible to turn down an extra $10,000," he said, noting that the figure equates to dozens of substitute days of coverage if not otherwise funded. Property committee chair Weidner, who introduced the motions, and other supporters emphasized the long-term budget relief and that the installations would be covered by a multi-decade contract.
Opponents focused on aesthetics and long-term visibility of panels. Board member Fried said he worried about how rooftop panels would look after 10–20 years and relayed constituent concern that panels could "deface" the carefully designed architecture of the elementary school. Fried added that public feedback he collected while canvassing was mixed and that the durability and long-term appearance of panels remained an open question.
The board additionally voted to table Motion 4, which concerned adding a ground array; staff clarified the ground array option required some roof-mounted installations to qualify.
Votes on the motions were recorded in roll-call form during the meeting. Motion 1 (including slanted roofs) failed on a roll-call; Motion 5 (flat surfaces only at the elementary school) passed; Motions 2 and 3 (flat surfaces at middle and high schools) passed. The board did not adopt the ground-array motion and indicated it could revisit that option later.
The property committee said vendors provided the estimated revenue figures and contract terms would include long-term access and service agreements; board members asked staff to follow up on aesthetic mitigation and long-term maintenance plans. The motion outcomes mean the district will proceed with contracting for flat-roof solar installations at the elementary, middle and high school buildings.