Council approves Task Order 5 to begin Burlington water main design
Summary
Facing MoDOT ownership complications for a Burlington cycle track, council approved Task Order 5 to separate and begin design of the Burlington Water Main replacement, with council direction to start design work ahead of final master‑plan numbers.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
Council authorized staff to proceed with Task Order 5 to treat the Burlington Water Main replacement as a separate project and begin design work.
Staff explained that MoDOT’s requirements and turnover have made the original plan to combine a cycle track and water main infeasible. Two MoDOT options—full transfer of ownership of Burlington or partial deeding of cycle‑track right‑of‑way—were described as placing unacceptable indemnity and maintenance obligations on the city. Given those constraints, staff recommended separating the water main project so the city could start design work without resolving MoDOT ownership questions.
Public works staff described the existing main as a mix of aged pipe (some sections about 110 years old) and collapsing 10‑inch sections; the council and staff discussed upsizing sections to 16‑inch or 24‑inch in parts of the alignment to meet current fire‑suppression and distribution needs. A motion to accept Task Order 5 was moved and seconded and then passed by voice vote; staff will begin design work and return with final costs for Council consideration.