Trillium Trail water-main funded through regional program; multiple sewer grant applications filed
Summary
City staff said the Trillium Trail water-main will be funded through the regional clean-water program and that bids will be advertised for award in June, with construction expected late summer; staff also submitted grants for sanitary-sewer design and pollution‑reduction work covering roughly 80 homes in the southwest quadrant.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
Don, representing the service/engineering side of city operations, briefed council on sewer and water projects. He said the Trillium Trail water‑main received funding through the Clean Water Main program and staff expect to advertise the contract for award in June; if awarded on schedule, construction could be completed in about a month and a half, putting final work in late summer.
Don also reported multiple sanitary‑sewer grant applications for a two‑phase approach: grants were submitted for the design phase and for a later construction phase to address about 80 homes in the southwest quadrant (Bell Court, part of Curtisdale and adjacent streets). He described additional grant pursuit to fund engineering for prioritized areas and pollution‑reduction work informed by stormwater testing at Summit Lane, Pine Tree and Landerwood Plaza corridors.
Don said the city will manage construction and that the regional partner approved the design; the partner will provide the funds for the full project and the city will handle construction oversight. Council discussed schedule and the mayor noted this program has contributed multiple millions toward past waterline replacements.
No final contract award was recorded during the meeting; staff requested authorization to proceed with advertising and anticipated returning to council for contract award.