Supervisors approve $33,197 change order for Pine Crest Foundation project in Waterloo
Summary
The board approved Change Order 005 to Peter's Construction for work on the Pine Crest Foundation project at 1407 Independence Avenue in Waterloo for $33,197 after a facilities manager detailed 11 adjustments including load testing of emergency exits and replacing low-flow flush valves that were causing double-flush complaints.
Get email alerts on the Contracts Construction topic
No spam. Unsubscribe anytime.
The Black Hawk County Board of Supervisors approved a $33,197 change order for the Pine Crest Foundation project at 1407 Independence Avenue, Waterloo, after a facilities manager detailed the reasons for the adjustments.
Carol Cornelius, the county’s facilities operations manager, told the board the change order contained 11 items ranging across structural, HVAC and painting work. She said one of the larger items was “doing load testing on 2 of the existing emergency exits” after the fire marshal requested the tests. Cornelius also said the project replaced flush valves in new restroom fixtures — switching from 1.28 gallons per flush to 1.6 gallons — because users reported having to double-flush.
Cornelius said the contractor, Peter’s Construction, and Envision Architecture worked to rearrange some exam rooms and reuse existing wall cutouts in a former VA building to reduce structural costs. Supervisors asked whether some wire-mold work was in new construction; Cornelius clarified it was run on the second floor west (the HHS side) to add lines without re-opening finished walls.
After discussion, the board moved, seconded and conducted a roll-call vote; each voting member answered in the affirmative and the Chair announced the resolution approved.
What it means: the approved change order addresses fire-marshal requests and user complaints at the Pine Crest site and preserves the construction schedule by avoiding more extensive rework. The project location and contractor were specified in the resolution. No dissent or recorded abstentions were indicated in the roll call at the meeting.
Sources: Project presentation and Q&A at the March 17 Board meeting; direct quotes from Carol Cornelius during the item.