RTA rep: Edmond–Norman commuter rail would cost roughly $500–$600 million; referendum targeted in 9–12 months
Summary
Marion Hutchinson, a Norman representative on 1 Transit (the RTA), told the Norman City Council the Edmond–Norman commuter rail would run on the BNSF corridor, include three Norman stations and cost about $500–$600 million (roughly half expected from FTA New Starts grants). The RTA is preparing for a public referendum within about a year.
Get email alerts on the Regional Transit topic
No spam. Unsubscribe anytime.
Marion Hutchinson, a Norman representative on the regional transit authority known as 1 Transit, told the Norman City Council on May 19 that planners are preparing to seek voter approval for an Edmond–Norman commuter rail line within roughly 9 to 12 months.
Hutchinson said the proposed North–South commuter rail would run in the BNSF corridor and include three Norman stations — near Tecumseh, downtown and south near Highway 9 — plus an OU stop at the Duck Pond. He said the RTA hopes to operate game‑day and event trains to serve University of Oklahoma events and other festivals.
“Right now you’re looking at $500 or $600 million to put all those improvements in on the BNSF corridor,” Hutchinson said, adding that about half of that sum would come from Federal Transit Administration New Starts grants. He said the authority is planning a conservative, phased build and that cities would acquire station properties while the RTA would construct the core system.
The presentation framed the project as a response to accelerating traffic congestion across the Oklahoma City metro: Hutchinson cited regional population growth projections — the metro could approach 2 million people by 2040 — and said transit can expand travel choices, support workforce mobility and spur transit‑oriented development around stations.
On operating plans, Hutchinson said the system would be set up initially for about 12 round trips per day, with higher frequency at peak hours and contractual options to expand to roughly 24 round trips per day. He said the RTA has been negotiating with BNSF for several years and expects the freight railroad to guarantee passenger service windows while RTA upgrades infrastructure (including double track and sidings) to protect freight capacity.
Councilors asked about station finishes and whether the historic downtown depot would be replaced; Hutchinson said cities would own station sites and could pay for branded or enhanced station treatments above a base package covered by the regional program. He also defended the timing, saying years of planning put the region in position to use federal grants and avoid the delays other metros faced.
Next steps listed by staff and Hutchinson included continued engineering, pursuing federal New Starts funding, coordinating station property acquisition with member cities and scheduling a coordinated referendum among Oklahoma City, Edmond and Norman city councils when the funding package is ready.
The council did not take formal action at the study session; Hutchinson said he was available to meet with council members individually for follow up.