Duncanville ISD board approves multiple bond-funded roof projects, renovations and a $1.6M change order

Duncanville Independent School District Board of Trustees · May 19, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Trustees unanimously approved awards for multi-campus roof replacements, an operations complex roof project, Maryfield Education Center renovations, and a not-to-exceed $1.6 million change order for Clint Q. Smith Early Learning Academy; most work is funded through bond proceeds.

The Duncanville ISD Board of Trustees approved several facilities contracts and a substantial change order, all described as bond-funded in the board presentation.

Roof projects: Mari (Mady) Zamora presented results of competitive procurement for multiple roof projects recommended by the bond committee. For Hyman Elementary the top-ranked proposal was listed in the evaluation as Trieland Roofing and Waterproofing; for Duncanville High School the top-ranked firm was listed as Alta Vista Roofing. The board moved to negotiate and enter agreements for the indicated vendors and approved the motion unanimously, 6–0. Zamora cited the RFP release and evaluation process and said the work would begin this summer with phased completion dates.

Operations complex: For the operations complex (warehouse, maintenance, transportation), CS Advantage USAA ranked highest on the RFP evaluation and was recommended at a cost of $571,000; trustees approved that award (6–0). During discussion the vice president confirmed the warranty period was 20 years.

Maryfield Education Center renovations: Following the board’s earlier decision to repurpose the facility to house Pace High School and Summit Education Center, the district solicited competitive sealed proposals; Picasso Contractors ranked first on the evaluation. Trustees approved negotiating and entering into an agreement with Picasso Contractors for the Maryfield renovations (6–0). The RFP was issued April 2 and closed April 23; the district received five proposals.

Clint Q. Smith Early Learning Academy change order: Project presenters said that unforeseen conditions discovered during renovation work require a second change order. Change order number 2 increases the project budget by a not-to-exceed $1,600,000; roughly $650,000–$750,000 of that amount was described as owner’s contingency and any unused portion will return to the district. The board approved the change order unanimously, 6–0, and project staff said they do not expect to exceed the $1.6 million request.

Why it matters: The approvals move multiple capital projects forward ahead of the next school year and use bond funds authorized by voters. Change orders and contractor selection decisions affect schedules, cost contingencies and small-business participation in district projects.

What to watch: Project schedules and final contract awards; the board packet cites bid-tabs and evaluation pages (board book references given in the presentation) for more details on scoring and final contract language.

Votes at a glance (selected): - Multi-campus roof replacement (Hyman Elementary and Duncanville High School): motion approved, 6–0. Presenter: Mari (Mady) Zamora. Reported amounts on bid tab: Hyman (recommended) $735,800; Duncanville High School (recommended) $3,500,000 (as reported in meeting presentation). - Operations complex roof replacement (CS Advantage USAA): awarded $571,000; vote 6–0. - Maryfield Education Center renovations (Picasso Contractors): motion approved, 6–0. - Clint Q. Smith Early Learning Academy Change Order #2: increase not to exceed $1,600,000; motion approved, 6–0.

Provenance: Facilities topics and votes are recorded in SEG 722–SEG 1103.