Evanston committee awards James Park renovation contract tied to $600,000 OSLAD grant
Summary
The Administration and Public Works Committee approved a roughly $1.8 million contract to renovate James Park, including pathways that must remain in the base bid to satisfy a $600,000 Illinois OSLAD grant; city staff said the scope means the city’s match will exceed the grant cap.
Get email alerts on the Parks And Recreation topic
No spam. Unsubscribe anytime.
The Evanston City Council’s Administration and Public Works Committee on May 11 approved a contract award for the James Park renovations and pathway improvements, a project tied to an Illinois Department of Natural Resources OSLAD grant. Paul Zamazak, the city’s economic development manager, said the grant carries a $600,000 maximum and the work bid includes playground, pathway circulation and sidewalk repairs adjacent to the fieldhouse.
Zamazak said the pathways could not be separated as an alternate because the city’s grant application included them. “We did tell them that would be part of the contract. So, we can’t separate it out that way,” he said. He added that including the pathway in the base bid generally produces better pricing than leaving it as an alternate.
Committee discussion identified total project costs in the packet at about $1.8 million plus additional items noted elsewhere on the agenda; Zamazak said the city entered the grant application understanding its share would exceed $600,000. Council members did not object and the motion to approve the contract passed by voice vote.
The contract brief identifies the work as playground and pathway replacement and pavement repairs to address ADA-related differential settlement near the fieldhouse. Zamazak also said the winning contractor is self-performing more than 25 percent of the work, though the packet did not list an exact percentage.
What happens next: the committee approved the contract and it will proceed as described in the purchasing documents; no additional committee conditions were recorded in the transcript.