Park County awards $196,940 contract to replace failing Lane Five culvert

Park County Board of County Commissioners · May 19, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

County engineers recommended and the Board of County Commissioners awarded a $196,940 contract to CK Civil of Cody to replace a failing culvert on Lane Five, citing the road’s role as a major local artery and the risk of a catastrophic washout.

Brian Edwards, Park County’s county engineer, told commissioners the failing culvert on Lane Five requires replacement and presented the procurement results after bids were advertised locally and on national plan rooms. “The apparent low bidder is CK Civil here out of Cody for $196,940,” Edwards said, noting staff corrected clerical math errors in competing bids before making a recommendation.

Edwards said contract documents include a schedule and liquidated-damages provisions, and he expects a start date after July 1 with roughly 60 days for completion. Commissioners stressed urgency: failing the culvert, they said, would close a major artery in the county’s north flat area and could create a prolonged access problem for residents. One commissioner noted the bids appear competitive and that reserves exist for catastrophic failures.

After questions about bid hold periods and schedules, a motion to award the contract to CK Civil for $196,940 was moved and seconded and the board carried the motion. The county engineer said the contractor is local to Park County and holds required documentation; final contract signing and any required preconstruction submittals will follow typical procurement procedures.

The board did not record a roll-call vote in the transcript; the motion passed by voice vote. Implementation steps include obtaining complete insurance and schedule submittals from the contractor and coordinating with county staff on traffic control during a two- to three-week full road closure anticipated during construction.