Secondary campus update: RFP for construction manager to push some early work to 2029, building start still planned for 2031
Summary
District staff said the board will run an RFP for a Construction Manager at Risk (CMAR) and, to allow a thorough procurement, will likely move some early site work from 2028 to 2029; design work will continue and the district still projects a building start in 2031.
Get email alerts on the Facilities Secondary Campus topic
No spam. Unsubscribe anytime.
District facilities staff told the board the new secondary campus schedule will shift modestly as the district runs a competitive RFP to select a Construction Manager at Risk (CMAR).
Mr. Whitel said the RFP will take roughly two to three months and the district expects to bring a recommended CMAR award to the August board meeting; securing a CMAR in August means that some early site work—previously discussed as beginning in 2028—would likely be delayed to 2029. Whitel emphasized that Brezlin will perform additional schematic design reviews at its cost before the CMAR comes on board to reduce imported fill, examine a partial three‑story option at the east classroom wing, evaluate ramps and lifts to lower first‑floor elevations, and explore eliminating an elevated patio to reduce impervious coverage.
Why it matters: the CMAR procurement and the additional schematic reviews are intended to reduce cost and complexity by testing alternatives before committing to mass earthwork and site relocation of athletic fields. Whitel said that, while some early phases move later, the district’s overall target to begin building construction in 2031 remains in place.
Quotes and attribution: “securing approval of the CMA in August would also mean waiting on approval of the architectural design work until August as well,” Mr. Whitel said, explaining the RFP timetable and downstream effects on early-phase scheduling.
Next steps: staff will issue the CMAR RFP, receive proposals over the summer and return with a recommended award in August; board action on the CMAR and associated architect approvals is planned for the August meeting.