Gurdon School District hears contractor as dozens of bids pour in for elementary addition
Summary
Board members were briefed on bidding for an elementary addition after the district solicited 19 trade packages and roughly 263 subcontractors; presenters said about 70–75 bids were received and staff will review bidders for coverage gaps and scheduling concerns.
Get email alerts on the Elementary Addition topic
No spam. Unsubscribe anytime.
The Gurdon School District Board of Directors on May 19 heard from the district’s construction team that the elementary addition project drew strong interest from contractors.
Jody, a board member, told the board the district sent bid invitations to “263 different subs” covering 19 trades and received “close to 70 bids — 70, 75, somewhere around in there,” leaving staff to vet responses for missing trades or duplicate bids. She said the formal bid opening was scheduled for the next day.
A project manager for the contractor NAPHOLS described logistical concerns the district should expect during construction, including long lead times for steel joists that will support the safe‑room deck and variability in availability for HVAC units. “Sometimes you can get them in six weeks, sometimes it might take, you know, 16,” the project manager said.
The contractor also discussed electrical work and transformer options. If a pole transformer can be used, supply is more readily available, the presenter said; a pad transformer can carry waits up to 52 weeks depending on ordering and utility schedules. The presenter additionally confirmed plans to fence and secure a materials storage area behind the site to reduce liability during football games and other events.
Board members and the presenter acknowledged weather and delivery lead times as scheduling risks and said staff will review each bidder’s schedule and submittals before recommending award.
What’s next: district staff will open bids as announced, evaluate responsiveness and scope coverage, and return to the board with recommended awards after vetting contractors and scheduling impacts.