Canton Local advances $19 million middle‑school agreement with state agency; maintenance‑tax resolution also approved
Summary
Board members heard administrators outline a $19 million middle school project (local share ~ $11 million; state share just under $7.8 million) and moved to adopt a resolution authorizing execution of the Ohio Facilities Construction Commission agreement and a companion resolution seeking a maintenance‑tax alternative because the district funded its local share without a bond issue.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
Administrators told the Canton Local Board on May 18 that the district’s middle school project has a total cost just over $19 million, with a local share of about $11 million and a state share just under $7.8 million. To preserve eligibility for state funding and to finalize project terms, the board was asked to approve a resolution authorizing execution of the Ohio Facilities Construction Commission (OFCC) project agreement.
Superintendent-level presenters explained the district funded its local share directly rather than issuing bonds and therefore must petition OFCC for a maintenance-tax alternative; that companion resolution would create a maintenance fund and set up transfers tied to levy results so the district can cover ongoing upkeep. The administration recommended board action on both resolutions; motions to act were made and seconded during the meeting.
The board discussed timing for receiving state funds and the mechanics of the maintenance fund; administrators said they are hopeful to receive state funding by the end of the calendar year but gave no firm date. The district presented the project budget breakdown and related exhibits to the board for review.
No formal vote tallies were recorded in the public transcript for the resolutions, and the transcript did not include a roll-call vote with named yes/no tallies in the excerpts provided; the board proceeded with motions to act on the items during the meeting.
Next steps cited by administrators included finalizing the OFCC agreement paperwork and implementing the maintenance-fund transfers as the district’s levy and funding timelines permit.