Council approves JDV conveyor purchase and BDP change order for water-reclamation upgrades

Post Falls City Council · May 19, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The council approved buying a JDV conveyor ($96,000 with contingency) and a change order with BDP Industries ($681,000) to add a second dewatering press, bringing the BDP contract near $1.45 million to support solids-handling improvements and project sequencing for 2027–2028.

City project staff asked the council to pre-purchase equipment and authorize a change order to keep the Water Reclamation Facility solids-handling improvements on schedule.

Andrew Arbini, projects division manager, said the BDP dewatering press and an associated conveyor are long-lead items needed to make project-one systems operational in early 2027. Staff competitively solicited quotes for the conveyor, received two responses and recommended a JDV unit at a low quote of $87,000; including contingency the requested authorization was $96,000. Council approved pre-procurement so the unit can be assigned to the contractor when construction begins.

For project two, Arbini requested a second BDP press to preserve redundancy and meet projected capacity. BDP had been previously declared a sole source because the city already operates BDP equipment and the vendor could honor prior pricing; staff solicited an alternative but found substantially higher cost. The requested change order was $681,000, bringing the total BDP contract to approximately $1.45 million. Council approved that change order as well.

Arbini explained that declining to purchase the conveyor would delay project-one startup by several months and ripple through the project schedule; project-two items may be procured under a later construction contract. Council voted in favor of both measures during roll call votes.