Elk County approves CDBG work-scope revision reducing bathroom size for FY2023 project
Summary
Becky Taylor told commissioners a state monitoring review required a work‑scope revision: a project bathroom was downsized from 144 sq ft unisex to a single‑occupant 65 sq ft facility; the board approved Resolution 2026‑04 by voice vote for audit documentation.
Get email alerts on the CDBG topic
No spam. Unsubscribe anytime.
The Elk County Board of Commissioners approved Resolution 2026‑04, a work‑scope revision required by state monitoring for a Community Development Block Grant (CDBG) project from the fiscal‑year 2023 plan.
Becky Taylor, identified in the meeting as county planning staff, told the board that the original bid process produced a single bid that was rejected and the project was subsequently rescoped. That rescoping reduced the bathroom included in the project from 144 square feet and a unisex layout to a 65‑square‑foot single‑occupant bathroom, Taylor said. She said the revision is needed to document the change for future audits and three‑year monitoring reviews.
A commissioner moved to approve Resolution 2026‑04; the motion was seconded and the resolution passed by a voice vote. The meeting record does not include a roll‑call tally or individual named votes.
The board did not discuss additional funding or amendments to the project scope during the vote. Taylor said the revision is administrative and intended to ensure the county has the required work‑scope documentation in its files for state monitoring.