Summary
Staff presented options for a potential pool at Willowwood: a neighborhood-scale pool (12,000—4,000 sq ft) estimated at $11M—5.5M plus $1M'M for parking, and a community-scale pool (16,000—8,000+ sq ft) estimated $14M—9.5M. Staff recommended pausing additional concept development until site assessment and Track 3 scaling are complete and returning to council in July.
Get email alerts on the Recreation topic
No spam. Unsubscribe anytime.
Marion City staff updated the council on work by the aquatic center steering committee and presented preliminary scales and cost magnitudes for a potential new pool at the Willowwood site.
Seth (staff) outlined two scales: a neighborhood pool (roughly 12,000—4,000 square feet, focused on toddler features and local use) and a community-scale pool that would serve a broader population (16,000—8,000 square feet or larger). Seth said the current Willowwood pool is about 13,000 square feet and that a neighborhood-scale replacement would be similar in footprint.
Estimated costs provided to council were: neighborhood-scale construction roughly $11 million to $15.5 million (site work and facility), with additional parking upgrades estimated at $1 million to $2 million if needed; community-scale replacements were shown as roughly $14 million to $19.5 million. Staff noted parking and traffic constraints at the Willowwood site make a larger community-scale facility less suitable there unless substantial parking changes are made.
Given outstanding work (a Willowwood site assessment, a Track 3 scaled plan and the existing maintenance/longevity analysis), staff recommended pausing further concept design for Willowwood and returning in July with all three tracks and written materials council can share with constituents. "From a staff recommendation, we would like to recommend pausing any further concepting until we get the other tracks caught up," Seth said.
Next steps: staff will complete the Willowwood assessment, provide the Track 3 revised plan and bring the three options back to council in July, and will provide summary materials for council members to use at public outreach such as the farmers market.