Summary
The San Antonio Board of Building and Standards on Nov. 13 ordered demolition of several vacant, fire‑damaged houses, approved a 30‑day repair order for one owner and rescheduled or amended actions on others after testimony from staff, owners and neighbors.
Get email alerts on the Code Enforcement topic
No spam. Unsubscribe anytime.
SAN ANTONIO — The San Antonio Board of Building and Standards on Nov. 13 reviewed a series of hazardous‑building cases and issued orders ranging from demolition to repair as staff presented photographs and inspection findings for each address.
Staff and inspectors opened the hearing with instructions for owners: deliver a scope of work, proof of financial ability and a schedule for repairs, and secure all required permits at the city development services office in San Antonio. “Pueden conseguir todos los permisos aquí… en San Antonio,” staff told the board during opening remarks.
At 3101 One Oak Drive, Crystal Town, dangerous‑structures official, described extensive fire and smoke damage, missing utilities and structural deterioration and told the board that no scope of work, engineer’s report or permits had been submitted. “El personal recomienda reparación,” Crystal Town said in presentation of the file, while police testimony documented long‑running neighborhood disturbances. Officer Anthony Peña told the panel the police unit had responded repeatedly: “Desde esta ocasión ha habido 30 llamadas para servicio de la policía desde marzo,” and referred to narcotics complaints and transient activity near a school crossing.
Neighbors and residents urged board action. Martin Corman, who lives about a block away, described safety concerns for children walking to the nearby elementary school and said the house had been a recurring neighborhood problem. After public comment and owner representation at the podium — including an attorney who said the owner is pursuing title and insurance issues — the board moved and voted to declare 3101 One Oak Drive a public nuisance and ordered demolition within 30 days. The motion carried unanimously.
The board took similar action at 2517 Ruiz Street after staff presented photos showing water and structural damage; owner Teresa Flores testified she lacked immediate funds but said she hoped to obtain financing to repair. Staff recommended demolition and the board voted 6–0 to demolish the structure within 30 days.
At 825 Moctezuma Street, staff recommended demolition of the principal structure and accessory. Representatives of Esperanza Community asked the board to delay demolition to allow the nonprofit time to pursue acquisition and rehabilitation. An initial motion to reschedule the case ended in a 3–3 tie and failed; the board then approved a motion (with an amendment requiring the property be posted as vacant and secured) to demolish the structures within 30 days, the motion passing 5–1.
For 601 South Hackberry, inspectors documented fire and water damage and missing utilities. Owner Angela German told the board she plans to use part of her retirement savings to finance repairs and asked for 30 days to obtain contractors’ estimates. The board found the property repairable and ordered repairs within 30 days; the motion passed unanimously.
At 9500 Simplicity Drive, staff recommended a partial demolition of a deteriorated attached garage and demolition of an accessory shed. The board approved demolition of the specified portions within 30 days and directed that utilities to the garage be disconnected before demolition.
At 4234 Wild Oak Drive the board approved a demolition order after staff described long‑term vacancy, water damage, debris and evidence of unauthorized entry; the motion passed 5–0.
What the board ordered (summary of actions): all demolition orders require the properties to be vacated, secured and cleared of debris within 30 days unless otherwise noted; the board also directed staff to coordinate next steps with property owners and the code officer in each case.
The meeting closed with administrative announcements, including the appointment of a new member to the panel and a posted application deadline for other openings.
Votes at a glance
- 3101 One Oak Drive — Order: demolition within 30 days; vote: 6–0. (Staff recommended demolition after evidence of fire damage, missing utilities and no permits submitted.) - 2517 Ruiz Street — Order: demolition within 30 days; vote: 6–0. (Owner present; staff recommended demolition.) - 825 Moctezuma Street — Order: demolition of main and accessory structures within 30 days, with vacancy notice and securing requirement; vote: 5–1 (one earlier reschedule motion tied 3–3 and failed). (Esperanza Community requested delay to seek rehabilitation funds.) - 601 South Hackberry — Order: repair within 30 days; vote: 6–0. (Owner Angela German committed to pursue financing and contractors.) - 9500 Simplicity Drive — Order: partial demolition of garage and demolition of accessory; utilities to demolished garage to be disconnected; vote: recorded in meeting (majority). - 4234 Wild Oak Drive — Order: demolition within 30 days; vote: 5–0.
Who spoke (selected): Crystal Town (dangerous‑structures official), Anthony Peña (police unit), Brian Garza (dangerous‑structures official), Cynthia Santana (dangerous‑structures official), Teresa Flores and Angela German (property owners), René González (Esperanza Community), Martin Corman (neighbor).
Why it matters: Board orders affect property conditions, neighborhood safety and the disposition of vacant, fire‑damaged houses near schools and residences; some owners said they are pursuing financing or title resolution while neighborhood advocates sought delays to allow nonprofit rehabilitation.
Next steps: Demolition and repair orders include 30‑day timelines and administrative follow‑up by code officers; owners were advised to submit scopes of work, financial proof and permit applications to development services.