KLJ outlines runway-extension options for Carter County airport; commissioners asked to seek operator letters
Summary
KLJ engineer Justin Zindel presented options to extend the county runway. Planners can justify a 575-foot extension now; longer extensions to serve medevac aircraft would require more justification, local share and possibly land acquisition. Staff recommended letters of intent from local operators to strengthen FAA justification.
Get email alerts on the Transportation topic
No spam. Unsubscribe anytime.
Justin Zindel of KLJ Engineering briefed the board on alternatives and preliminary cost estimates for extending the county airport runway. Current data justify a 575-foot extension under an AirTract 402 analysis, which would move the runway from 3,800 feet to roughly 4,375 feet. Extending the runway to serve medical-evac aircraft (King Air/PC-12) or to reach roughly 761–807 feet requires additional justification and would increase ineligible local costs.
Zindel said the engineering/construction estimate to reach the 575-foot level is eligible for federal funding and that adding further footage could raise ineligible local-share costs (examples provided in the briefing: an extra roughly $109,000 and another smaller ineligible amount of about $53,000 for certain elements). He estimated a worst-case local share in the low hundreds of thousands (he cited a figure around $332,600 in one scenario) plus land-acquisition costs. Zindel recommended collecting letters of intent from local operators — including an agricultural operator and air-ambulance providers — to reinforce justification to the FAA. He proposed a follow-up meeting with FAA planners, Montana Aeronautics, and county staff near the end of May to finalize CIP submissions and environmental-path options.
Commissioners discussed options to acquire land now and run environmental review later, the timing of CIP (capital-improvement program) deadlines and potential use of entitlements or short-term county funding to advance design work.