SWCD warns of easement limits as ONCOR/LCRA 765 kV route is discussed
Summary
A McCulloch County SWCD representative told the Commissioner’s Court that permanent SWCD easements restrict construction that could alter flood control dams and reported five dams were surveilled after recent rains and "held as designed." The court received the presentation but took no formal action on routing.
Get email alerts on the Transmission Line topic
No spam. Unsubscribe anytime.
Mark Moseley of the McCulloch County Soil & Water Conservation District told the Commissioner’s Court on Aug. 11 that SWCD holds permanent easements on conservation dams and that prior SWCD approval is required before structures are added in easement areas.
Moseley discussed the ONCOR/LCRA proposed 765 kV transmission line route and cautioned that some easements restrict construction because of potential impacts on natural water flow for flood control. He told the court that Dam Watch had "tagged 5 dams in the last rains event for surveillance" and reported the dams "held as designed."
Why it matters: easement restrictions can limit where transmission infrastructure may be built or require additional approvals and engineering to protect flood-control structures. A member of the public, Bruce James, asked the court to support a resolution opposing the route; the court did not take action on a resolution during the meeting.
What happened next: the presentation informed the court of SWCD’s role and easement constraints; no motion or formal route action was recorded.
Attribution: Mark Moseley delivered the SWCD presentation; the court received the report and discussed potential concerns about easement limits and flood-control impacts.