Finance Committee reviews FY2027 budget that draws $7.2 million from reserves and proposes 5.5% water-rate increases

Mundelein Village Finance Committee · March 23, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Mundelein Village Finance Committee heard a presentation on the proposed fiscal year 2027 budget March 23; staff proposed a balanced $38.8 million revenue forecast against an $87–88 million total budget that relies on a $7.2 million reserve draw, funds four new full-time positions and includes a 5.5% annual water-rate increase for five years.

The Mundelein Village Finance Committee on March 23 reviewed a proposed fiscal year 2027 budget that staff said would be balanced against a conservative $38.8 million revenue estimate but rely on a $7.2 million draw from reserves to cover planned capital and personnel costs.

Mr. Gunther, who presented the materials to the committee, said FY26 revenues are tracking about $2,000,000 above prior projections and expenditures about $1,000,000 below, producing a roughly $3–3.5 million positive swing heading into the April 30 year end. "Revenues are coming in just about $2,000,000 higher than what was projected," Gunther said.

Gunther told trustees the village's revenue mix has changed: sales tax receipts now surpass property tax revenue, and anticipated state reporting changes will fold use tax into the sales-tax category. He said the draft FY27 budget assumes approximately $38.8 million in revenues and a total budget of roughly $87–88 million; that year-over-year increase reflects large multi-year projects, notably a $4 million water-meter project and about $1.9 million in capital work at the Archer Business Center.

To balance the proposed FY27 budget, Gunther said staff plan to use $7,200,000 from reserves. He provided a breakdown: about $2.3 million toward personnel obligations (wage increases and pension costs), roughly $1,000,000 attributable to rising insurance premiums, $1.9 million for capital improvements at the Archer Business Center (including a roof replacement), and a $1.3 million transfer from the general fund to an equipment fund to pre-fund vehicles and other capital needs. "That $7,200,000 is being used from reserves to balance that budget for this year," he said.

Gunther recommended adding four full-time equivalent positions in FY27 — one police officer, one firefighter, one event planner and one flexible position to be allocated where needed — while noting that police had requested five new officers but staff proposed funding one. He said roadwork remains a priority, with about $5.6 million budgeted for resurfacing, reconstruction and associated projects, and that recent bid savings on MFT-funded work allowed the village to add streets to this year's program.

On utilities, Gunther said the board previously agreed to a five-year plan that would impose 5.5% annual increases to water rates to help fund operational needs and the water-meter project; staff will present a fee ordinance reflecting that rate at a future board meeting.

Trustee Lambert asked whether the planned reserve draw represented recurring personnel costs that would require future reserve draws. Gunther replied that most of the $7.2 million covers nonrecurring capital (roof, equipment fund, water-meter project), though some components — notably pension and insurance obligations — are ongoing and less predictable.

Gunther also described the Archer Business Center as an ongoing financial challenge: staff have added tenants but vacancies persist, and water intrusion and an aging roof have required interim repairs. He said the village is marketing the property and seeking a long-term solution but included a one-time $1.9 million infusion in the proposed budget as a contingency.

Committee members present indicated they were comfortable forwarding the proposed FY27 budget to the full Village Board for consideration at its April 13 meeting.

Votes at a glance: The committee approved the Finance Committee meeting minutes from Aug. 25, 2025, by voice vote earlier in the meeting. The committee later adjourned by voice vote.