Committee trims road, sidewalk and sign funding; shifts select items into bond consideration
Summary
The committee removed a $25,000 dirt-section paving item on Ossipee Hill Road (3–1), deferred $50,000 in sidewalks, set multiple CIP lines to zero to include in a bond, and approved an overall road upgrades subtotal of $191,000.
Get email alerts on the Roads And Public Works topic
No spam. Unsubscribe anytime.
The Budget Committee reviewed and cut several capital items affecting roads, sidewalks and municipal signage.
On roadway work, members debated initial paving for a 1,600-foot dirt section of Ossipee Hill Road. Concerns included limited house counts, bus routing and a difficult intersection at Strong Mill Brook Road. A motion to remove the $25,000 project for Ossipee Hill Road passed 3–1. Committee discussion stressed that while the dirt section is used, a lack of adjacent houses and safety trade-offs led some members to remove the line this year.
The committee also reduced the septic line to $2,500 after noting video inspections and potential savings; that motion passed unanimously 4–0. For sidewalks (line 523), members decided to defer the $50,000 line this year and to consider sidewalks later; motion to cut sidewalks to $0 passed 4–0.
Signage funding (line 510) was discussed at length. Members compared lower-cost moving-letter signs to higher-end, town-branded signs and discussed DOT restrictions on moving letters. Given fundraising options and design considerations, the committee voted 4–0 to move the sign line to $0 this year and to consider fundraising/reserve saving for a higher-quality sign later.
Finally, the committee set its roads upgrades subtotal at $191,000 (down from earlier figures) and agreed to prepare the CIP package for joint review with the selectmen.