Stevens County approves two ditch‑outlet petitions and hires contractor to repair century‑old tile in Ditch 14
Summary
At public hearings the board approved petitions to include parcels into County Ditch 1 and County Ditch 5 watersheds (under Minn. Stat. 103E.401) with viewer benefit and assessment calculations; the board also awarded a board‑ordered repair contract for County Ditch 14 to Wolf (low bidder) for about $54,500.
Get email alerts on the Water Management topic
No spam. Unsubscribe anytime.
Stevens County commissioners approved two ditch‑outlet petitions during consecutive public hearings and authorized a board‑ordered repair on County Ditch 14.
Ditch outlets: Ditch inspector Scott Erickson presented two petitions filed under Minnesota Statute 103E.401. For County Ditch 1, viewers determined the 40‑acre parcel being added had an equivalent of 4 benefit acres at the 100% rate (viewer-calculated dollar benefit listed as $400) and an outlet fee of $60 ($15/acre). For County Ditch 5, staff presented viewer calculations to re‑include approximately 66.69 acres previously removed during a redetermination; viewers produced benefit and assessment figures for the returning acres and related percentages and assessment amounts. The board opened each hearing for public comment, recorded one landowner inquiry for Ditch 5 (a single phone call expressing concern about fair share), and then approved both outlets after findings were read.
Ditch 14 repair contract: Scott also reported longstanding failures in County Ditch 14 tile (a roughly 110‑year‑old plate-tile system), including collapsed/failed sections and blockages that left acres underwater. The county solicited bids for a full repair; only one responsive bid was received and the board approved hiring Wolf (listed in the packet variously as 'Wolf Tyler' and 'Wolf Tiling') for the work. The meeting record cites the low bid at $54,500 and the board approved the motion to hire that contractor.
Why it matters: the outlet decisions adjust who pays into county drainage systems and can change assessment liabilities for landowners; the Ditch 14 repair is intended to restore drainage for several hundred acres that depend on the tile outlet.
Next steps: staff will record the viewer reports and assessment schedules and execute the repair contract; the board ordered the repair without a petition because benefits were limited within the system.
(Provenance: public hearings and motions recorded in the meeting minutes.)