Ceres council approves nearly $5 million GMP for wastewater solar project to cut energy costs

Ceres City Council · March 24, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The council approved a guaranteed maximum price of $4,988,000 and a plan to install roughly 995 kilowatts of solar at the wastewater treatment plant, projected to offset about 50% of plant power and deliver lifecycle energy savings of about $8.6 million.

The Ceres City Council on March 23 approved moving forward with a solar-plus-energy project aimed at reducing the wastewater-treatment plant's electricity costs.

Staff said the proposed solar array is approximately 995 kilowatts (just under 1 megawatt) and will offset roughly half of the plant's power needs. The contract amendment sets a guaranteed maximum price (GMP) of $4,988,000 for the system; staff said the project was budgeted in FY26 and will be paid from the sewer fund rather than the general fund.

City staff outlined a projected lifecycle energy savings of about $8.6 million and estimated net positive cash flow of roughly $3.5 million after federal investment tax credits. The timeline presented called for ordering long-lead items next month, construction from June through November 2026, and operational status by late 2026 or the first quarter of 2027.

Council members discussed warranty terms, the absence of a contingency in the amendment, and the city's exposure if the project were canceled after design work. The motion to move forward with the solar project passed 3'' 2 on a roll call vote.

Staff said standard equipment warranties and a guaranteed maximum price reduce some risks, and that project funding was appropriated in the FY26 budget. Follow-up items include providing comparative cost/savings analyses to council members and finalizing the guaranteed maximum price details for the wastewater-treatment plant expansion.