Highway official warns of recurring Plankenhorn Road damage; board approves advertising fuel and mowing bids
Summary
The highway department reported heavy farm machinery and trucks have repeatedly damaged Plankenhorn Road and asked the board to advertise fuel bids and a mowing contract and to re-up the 284 agreement; the department plans repairs and outreach to the farm to limit future damage.
Get email alerts on the Transportation Infrastructure topic
No spam. Unsubscribe anytime.
The highway representative told the board spring work is underway—hauling sand, repairing drainage and damaged culverts—and requested formal approval to publish the town’s fuel bid advertisement for two weeks and to re-advertise mowing bids unchanged from last year.
The highway official raised a recurring problem on Plankenhorn Road, saying heavy farm machinery and trucks have destroyed sections of the roadway each spring. “The highway department is currently coming up with a plan to fix it, and we also will be in contact with the farm to see what we can do that really prevents us from happening every spring,” the official said. The official told the board the church had filed a complaint and pledged a repair plan that may include routing heavy traffic to less sensitive sections of the road.
The board considered an updated agreement (a re‑up of the 284 agreement between the highway department and the board) with only the amount changed due to general repairs increasing by $15,000 in the budget. Members agreed to sign the amended paperwork and proceed with required advertising for fuel and mowing bids.
No formal procurement award was made at the meeting; the board approved motions to proceed with advertisement and to sign the updated agreement so procurement may move forward as scheduled.