Facilities update: athletic fields near completion, Bear Hill projects and change orders reviewed
Summary
The facilities committee reported athletic fields are largely complete, approved small change orders, discussed three pending change orders and recommended leasing fiber for Bear Hill after no bids; summer infrastructure work and consultant fees were summarized.
Get email alerts on the Facilities topic
No spam. Unsubscribe anytime.
Vice president and facilities chair Mr. Hong summarized the May 12 facilities committee meeting and construction status for summer 2026.
Mr. Hong said the athletic fields project is mostly complete and fields are in use; project photographs and video are available on the district website. The committee reviewed a small change order of $1,597.69 for installing new chair and platform lifts at Hillside and New Eagle elementary schools and recommended three pending change orders totaling $50,549.22 related to connecting building drains to stormwater management systems.
The Bear Hill Elementary project was updated; Dr. Semendera described a change order for steel beams and related projected costs and the committee indicated final change orders would be added to the consent agenda when available. The committee discussed options for fiber‑optic service to Bear Hill and recommended leasing fiber after no bids were received to support reliable Internet service.
Committee materials listed a summer infrastructure work total of $4,416,646 and a fee letter from architect Hegendorf & Schalld of $320,850. One figure in the packet was transcribed as $200,057,070,224 (appears inconsistent with other budget lines); that number appears to be a transcription error in the meeting transcript and has been flagged for clarification with district staff and the posted bid documents.
The committee also reviewed a request from Amber Osborne, executive director of the Easttown Library, for an expansion adjacent to district property; the committee expressed interest in future discussions.