Campbell Avenue extension advances with federal discretionary grant and 60% plans

Town of Sahuarita Town Council · May 27, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Town staff presented 60% plans for the Campbell Avenue extension, a nearly one-mile north-south road with a multiuse path; preliminary cost estimate $8.7 million with $3 million in federal discretionary funds, county/town impact fees and RTA participation. ADOT review and environmental work are underway; obligation deadline for federal funds is Sept. 30, 2027.

Town staff presented 60%-complete plans for the Campbell Avenue extension at the May 26 meeting and outlined schedule, design and funding. The approximately one-mile project will extend Campbell Avenue from Tunnel Canyon Place to Josephine Canyon with two 11-foot lanes, 6-foot paved shoulders, a 12-foot multiuse path on the west side and drainage improvements using an eight-cell box culvert for wash crossings.

Project manager (Cheryl) and Deputy Public Works Director Daniel Logan said the project has an estimated preliminary cost of $8.7 million. Funding sources include a $3 million federal discretionary grant, Santa Cruz impact fees, town and Pima County local funds and RTA allocations. ADOT (on behalf of FHWA) is reviewing environmental materials; the town is seeking a categorical exclusion to speed federal review but has completed biological and cultural reports and awaits ADOT comments on the biological evaluation.

Key schedule points: 60% plans completed and under review; final plans targeted by February 2027; ADOT acceptance of plans targeted for April 2027; federal funds must be obligated by Sept. 30, 2027. If obligation and reviews occur as planned, construction could take 6 to 8 months once started.

Councilmembers discussed the "good with the bad" of federal funds (added oversight and compliance requirements) and confirmed rights-of-way, drainage easements and cultural and native-plant inventories have been addressed in initial reviews. Staff noted mitigation elements such as native, drought-tolerant landscaping and pedestrian/bicycle accommodations.

The council did not take a vote on construction authorization that night; the presentation provided the current design, environmental coordination status and next steps toward obligating federal funds and starting construction.