Dayton council accepts preliminary McNeil Park water‑tower report; staff to return with final design
Summary
City staff presented a preliminary design locating an elevated water tower at McNeil Park to improve emergency storage and system reliability; council accepted the report and asked staff for renderings, final cost detail and follow‑up on grant match and prevailing‑wage implications.
Get email alerts on the Water Infrastructure topic
No spam. Unsubscribe anytime.
City staff presented and the Dayton City Council accepted a preliminary design and siting report for a water tower proposed at McNeil Park, a project intended to add emergency storage and steady distribution to the city’s small, city‑owned water system.
The council heard from staff that the village area served by the system currently has about 250 services supplied by two wells and a small 2,000‑gallon tank that provides pressure but not adequate emergency volume. Staff recommended an elevated storage tower to provide fire flow and operational resiliency during outages or maintenance, and described pipe‑network upgrades — including a proposed 12‑inch trunk main installed largely by directional drill — needed to reliably fill and operate the tower.
Why it matters: staff said the preferred McNeil Park location balances topography and system hydraulics and avoids land‑acquisition costs associated with a southerly private parcel. The estimated project cost in staff’s presentation was about $2.8 million for the tower and trunk main (an earlier CIP number showed roughly $3.6 million); staff noted that state bonding money of roughly $3,000,000 had been awarded, and that federal/state clauses tied to that funding (notably prevailing‑wage requirements and potential Buy American steel provisions) could change final costs. Staff said Buy American likely would not apply but prevailing‑wage rules probably will and that the team continues to refine estimates.
Council members asked for visual renderings of the tower from town entry points and for a clearer cost‑range before final design. One councilor raised skyline and aesthetics concerns because the preferred site sits near the town’s historic church steeple; another asked for comparisons to recent local tower projects and for more detail on footing costs and height tradeoffs. Staff said the tower would likely be in the 120–140 foot height range and that darker paint schemes may hide staining better but increase repainting costs.
The council moved and the motion to accept the report passed 5‑0. Staff will return with final design proposals, visuals from multiple viewpoints, refined cost estimates (including any prevailing‑wage premium) and recommended paint/logo treatment for council input.
Representative quote: “We left it high intentionally because we weren't really sure what those [prevailing‑wage/Buy American] costs would be,” said the presenting staff member, noting those clauses could add roughly a half‑million dollars to the project in initial estimates.
Next steps: staff will prepare final design materials and cost updates for a future council meeting; if state bonding language requires a local match staff will report back on match requirements and timing.