Ashwaubenon board approves Winding Creek Estates PUD extension, final plat and development agreement
Summary
The board approved a 15‑month PUD extension, the final subdivision plat (with staff conditions and a $46,004.95 park fee) and a development agreement for Winding Creek Estates; a developer performance agreement timeline amendment for MultiPond America was also approved with new milestone dates through 2029.
Get email alerts on the Winding Creek Development topic
No spam. Unsubscribe anytime.
The Village Board approved a package of actions May 26 clearing the way for the Winding Creek Estates residential development.
Planning staff described the project as a mixed single‑family, attached townhome and multifamily development. The applicant received preliminary PUD approval in February 2025; because construction had not begun within one year, the developer requested an extension. The board approved a 15‑month Planned Unit Development extension to accommodate bidding, winter, and a spring start.
The final subdivision plat was approved with staff conditions including a required stormwater management report and erosion control plan, confirmation of rear yard drainage for specified lots, a potential stormwater facility for additional lots, a 30‑foot easement for a Newwater interceptor sewer if needed, and payment of $46,004.95 in park fees.
Staff also presented and the board adopted a development agreement that defines utility, road and infrastructure responsibilities, construction warranty and a completion guarantee secured by a certificate of deposit at 120% of the required amount. The board approved recommended exhibit additions (exhibit C: improvements chart; exhibit D: financial institution info for the completion guarantee) and removed a requirement for a personal guarantee after staff review.
Separately, the board approved an amended developer performance agreement timeline for a different parcel sold to MultiPond America, moving submittal and construction deadlines out to 2027–2029. Under that amendment MultiPond must submit site plan/design review materials by 03/31/2027, commence construction no later than 11/01/2027 and obtain a certificate of occupancy by 02/01/2029, or risk the village pulling the property back under the development agreement terms.
What happens next: Staff will monitor compliance with the development agreement and the phased action items; Brown County Planning Commission approval was identified as a required next step for the final plat.