Council members heard that a proposed 8-foot Mount Hope trail connection would close a gap in the city's trail network but likely requires moving a 3–4-foot retaining wall; staff estimated the connection at roughly $500,000 and will return with refined survey drawings and cost options, including narrower lane geometry to avoid wall replacement.
Get email alerts on the Streets topic
No spam. Unsubscribe anytime.
City of Carver staff on Monday reviewed the 2026 Street Project and asked the council to consider design options for a trail connection on Mount Hope Road that would link Lions Park to downtown.
Aaron, the staff presenter, told council members the project is split into two packages: local street maintenance in Carver Bluffs and a larger state-aid reclamation on Mount Hope Road. He said the Mount Hope segment is costly in part because topography forces hard choices: the existing retaining wall sits about 3–4 feet behind the curb, and to meet state-aid trail standards the city would need about 10 feet behind the curb (an 8-foot trail plus a 2-foot clear zone). "The in-place retaining wall is situated about 3 to 4 feet behind the curb today," Aaron said, explaining why the wall likely must be moved for a standard 8-foot trail.
The staff estimate for the trail connection was presented at about $500,000. Council members emphasized safety and connectivity, noting the route would provide a safer pedestrian and bicycle link from neighborhoods downhill into downtown. One council member stressed that children in the area use the corridor and said a safe connection was a high priority.
Council members pressed staff about alternatives that could reduce cost or avoid replacing the retaining wall. Options discussed included building a narrower sidewalk section where feasible, moving the road slightly, shifting the trail to the west side, narrowing lane width in a short segment and reducing on-street parking, or staging work to defer some components. Staff cautioned that state-aid funding carries strict standards: "For it to meet a trail standard, it has to be 8 feet wide," Aaron said, and lowering the section to a sidewalk could jeopardize state-aid trail funding or change the project type.
Staff said they already have a survey and will prepare refined plan drawings and revised cost estimates for the council. The city’s funding approach for the broader 2026 project combines three buckets: the local street maintenance fund for Carver Bluffs work, state-aid funds for the Mount Hope reclamation, and utility enterprise funds for minor utility work; staff noted the $1.6 million line item under discussion did not include the trail work as presented.
Council direction: members asked staff to return with creative engineering alternatives (including possible lane-width changes and a refined net measurement on site) and to present the options at a January work session so the council could decide whether to authorize plans and specifications this winter for summer 2026 construction.