Upper Chichester approves Kingsman Park payments, moves forward on CAADC event space and applies for dog‑park grant
Summary
The board approved a small change order and a $208,004.42 payment for Kingsman Park, authorized intent to award a $382,028 contract for the CAADC event space, and voted to apply for $121,411.25 in DCED grant funding for the Fury Road dog park amid questions over whether one or two fields are affected.
Get email alerts on the Parks And Recreation topic
No spam. Unsubscribe anytime.
Upper Chichester commissioners approved late‑stage payments and contract actions for several park and recreation projects at their May 27 meeting, and voted to apply for a state grant for a dog park despite a remaining design question.
Commissioner Brett Hankins presented change order No. 9 for Ernel Company Inc. for the Kingsman Park project in the amount of $2,820 and a payment request No. 11 for $208,004.42; both motions were moved, seconded and approved by voice vote.
Township engineer Andrew Pokal described planned improvements tied to a separate CAADC event space contract Ernel Company submitted for the base bid and add alternates 2–4 totaling $382,028, saying, “So, this is hardscaping improvements … there's drainage improvements, addition of ADA parking spaces, some landscaping, and … the hardscape.” The board voted to authorize intent to award that contract.
On the Fury Road dog park, the board approved a resolution to apply to the Pennsylvania Department of Community and Economic Development’s Greenways, Trails and Recreation grant program for $121,411.25. Several commissioners asked whether the project would remove one or two existing fields; Commissioner Hankins confirmed the current understanding is that it affects one field, while staff cautioned the design is still at concept stage and can be adjusted without jeopardizing the grant request.
The Kingsman Park update also noted the pickleball courts are open while the playground remained closed pending final signage and punch‑list work. No public comment was recorded on these items. The motions carried by voice vote; the transcript does not include a roll‑call breakdown.