Canton approves $28,540 culvert pay application tied to 2024 flood repairs
Summary
The commission approved a $28,540 pay application for rubble-site culvert replacement, submitted by ISG on behalf of the contractor; staff said the cost had been submitted to FEMA and that FEMA had pre-paid based on estimates.
Get email alerts on the Public Works topic
No spam. Unsubscribe anytime.
The Canton commission approved a pay application of $28,540 for the rubble-site culvert replacement, a project that staff said was damaged during the 2024 flood. Staff reported that ISG submitted the application on behalf of the contractor and that the total project cost had been submitted to FEMA; commissioners understood FEMA had pre-paid based on an earlier estimate.
Commissioners discussed whether FEMA’s estimate matched the invoiced amount and confirmed that the single-event payment was a one-time application tied to the 2024 damage. The motion to approve the pay application carried on a roll-call vote.