Clear Creek Amana board authorizes about $17.52 million in GO bonds and approves construction contracts for middle/high school additions

Clear Creek Amana Community School District Board of Education · March 26, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Clear Creek Amana school board voted to authorize roughly $17,520,000 in general‑obligation bonds to fund middle- and high‑school additions and approved related vendor contracts and the amended construction‑representative contract. Bids are scheduled for spring with construction to begin this summer.

The Clear Creek Amana Community School District board on Wednesday approved a resolution authorizing the issuance of approximately $17,520,000 in general obligation school bonds, series 2026A, to fund the planned middle‑ and high‑school additions and related work.

Board members voted by voice to pass the resolution after project consultants reviewed the design status and schedule. The board also approved contract quotes for facility work — including locker replacements at Clear Creek Elementary and a track refurbishment — an engagement letter for disclosure counsel and an amended contract for the district’s on‑site construction representative.

Project consultant updates described the work as near the end of the construction document phase: 90% drawings are submitted for review, civil and structural teams are finalizing stormwater and permitting details, mechanical and electrical teams are coordinating utility and equipment connections, and the architectural team is finishing roof and demolition details. The team said it will present completed documents so the board can authorize going to bid at the next business meeting on April 15.

Key dates presented to the board include an anticipated bid opening on May 14, bid consideration and award on May 20, contractor mobilization starting June 2 and target substantial completion for the building additions on July 16, 2027. The consultant cautioned the board that material supply constraints (for example, precast panels) and regional construction demand could affect schedule or cost.

The board approved multiple action items by voice vote during the meeting: a quote of $48,435 for new lockers at Clear Creek Elementary, a quote to refurbish the high‑school track to Fisher Tracks (transcript lists amount as $127,000 $397), an LED lighting upgrade for the high school, an engagement letter with Ehlers and Cooney to act as disclosure counsel for the bond issuance, and an amended contract for Ray Willoughby to serve as construction representative for the project. The board also approved a final payout for a Clear Creek Elementary playground project in the amount of $7,600.

When asked about budget, a project representative said the district carried a standard 5% design contingency and that, at present, the project was tracking on budget; expanded scope items (the industrial technology alternate) could require additional funding. The financial adviser’s presentation to the board estimated spendable proceeds at closing and discussed debt‑service capacity prior to sale.

The bond resolution now allows staff to proceed with finalizing sale details and submitting plans to plan houses if the board moves forward on April 15. The board did not record roll‑call votes by name in the transcript; multiple motions passed by unanimous voice votes recorded as "Aye."