Eastport‑South Manor CSD gets detailed capital‑project update; phase‑2 work to continue into 2027

Eastport-South Manor Central School District Board of Education · May 20, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

District contractors reported progress on the high‑school addition and interior renovations, presented phase‑2 budget allocations (including a $500,000 garage set‑aside) and reiterated a projected target completion around September 2027 while board members requested a more granular July schedule.

Park East Construction and H2 Webb Architects presented the monthly capital‑project report, saying phase 1 is closed and phase 2 remains active with multiple workstreams across the high‑school addition and interior renovations.

Contractors reported that the addition and alterations are nearing substantial completion (addition ~85% complete; alterations about 97% near finish) and interior renovations are ongoing (reported around 40% for current interior phases). The district had previously shown a budget surplus close to $4,000,000; presenters said much of that was allocated to planned items including a high‑school storage garage and technology purchases, with a $500,000 set‑aside for the garage.

Architects described technical details raised by board members: a required fire separation between the new addition and existing building, a coping installation and central roof drains with tapered insulation to manage water, and newly added floor drains for the planned aquaponics lab. On electrical and safety questions, a contractor said he would "confirm with the electrical engineer" on receptacle placements and GFCI needs.

Board members requested a more granular schedule ahead of July updates to show which work will be completed during school breaks and which will occur over the next 18 months. Contractors reiterated a September 2027 target date for full project completion but said some elements could finish sooner.