Miller County discusses fuel-station pump, road-equipment options and P25 radio go-live
Summary
Commissioners discussed adding a diesel-side pump to the county fueling station to ease backups, reviewed options and quotes for road equipment and repairs including a downed unit facing a costly hydraulic repair, and heard that the county’s P25 radio system is targeting an April 8 go-live.
Get email alerts on the County Operations topic
No spam. Unsubscribe anytime.
Miller County commissioners heard operational updates on the county fueling station, heavy-equipment maintenance and a regional radio upgrade.
Chair reported the county is considering adding a regular pump to the diesel side of the county fueling station to reduce vehicle backups and said the county dispenses roughly 350,000 gallons of unleaded fuel compared with about 182,000 gallons of diesel annually. “We’re selling double the unleaded,” the Chair said while explaining the need for an additional pump.
Staff described a recent equipment outage: unit 309 has been down while mechanics diagnose a hydraulic fault. A staff member said the hydraulic pump part under consideration would cost about $67,000 and recommended diagnosing the exact failing component rather than replacing multiple parts preemptively. The staff member also reviewed multiple vendor quotes for road machinery (brands discussed included Eagle and MowerMax), noted trade-offs such as wiring and air-conditioning serviceability, and recommended examining warranty terms (for example, 7,500-hour warranties on leased machines) before deciding whether to buy or lease.
Cody, a county staff member, updated commissioners on the county’s P25 radio system: installation in patrol cars and fire units is complete, portable radios are programmed, antennas are scheduled for installation next week, and testing is planned for late March and early April with a target go-live date of April 8. Cody said the P25 system will enable communications with surrounding counties and the state patrol on compatible channels.
No formal votes or purchase authorizations for equipment or the fueling-station pump were recorded in the transcript; commissioners asked staff to gather additional diagrams and quotes and return with updated information for later consideration.
The meeting recessed into an executive session to discuss personnel and concluded with adjournment.