Council OKs final change order, reduces Paroon Road/Ravine Drive contract
Summary
Council approved Ordinance 82 to authorize a final change order that reduces the contract for the Paroon Road and Ravine Drive intersection project by roughly $140,474.98, yielding a reported final contract amount of $1,250,686.75.
Get email alerts on the Public Works Change Order topic
No spam. Unsubscribe anytime.
Public works presenter Shaw reported on Change Order No. 2 (final) for the Paroon Road and Ravine Drive intersection-improvement project. Shaw said project adjustments resulted in a net decrease to the contract, reporting an additional reduction of $141,221.98 and a final contract amount of $1,250,686.75 — about 10.8% under the original awarded price. Council member Richardson read the ordinance authorizing the change order and moved its passage as an emergency measure; the council approved Ordinance 82 by voice vote.
Richardson summarized the change-order figures in his reading of the ordinance: a decrease in the contract amount by $140,474.98 as stated in the ordinance text, and council proceeded to approve the measure.
The reporter noted the project closed with a net contract decrease and no further action was recorded at the meeting beyond ordinance approval.