Residents urge faster geotechnical reviews to preserve FEMA reimbursement; staff says capacity has expanded

Malibu City Planning Commission · February 3, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Public commenters urged the commission to adopt prescriptive geotechnical calculations to speed rebuilds and protect FEMA reimbursement; staff reported rebuilding statistics and said it has added capacity and consultant support to meet turnaround goals.

At the Feb. 2 Planning Commission meeting, public comment and staff reports focused on post‑fire rebuilding progress and delays tied to geotechnical review. Joe Drummond told commissioners the presidential executive order on wildfire recovery requires cities to demonstrate visible recovery at scale to preserve FEMA reimbursement and argued that prescriptive geotechnical calculations would speed rebuilding without compromising safety.

Drummond said geotechnical review routinely takes eight months or more for like‑for‑like rebuilds and that a prescriptive, conservative pathway (using area‑wide geotechnical data and conservative assumptions) is already allowed under State building codes. He urged the city to adopt a prescriptive option for stable lots to show visible recovery and avoid jeopardizing federal reimbursement (~$15 million referenced by a commenter).

Planning staff responded with updated rebuild dashboard statistics: 522 building permits issued to date, 153 planning approvals (with a 5‑approval increase since the last commission), about 70 planning applications under review, and roughly 25 building permits issued recently. Staff said a dedicated rebuild team operates separate from day‑to‑day planning, that they have hired additional staff and a larger geotechnical review firm, and that they expect to meet their 10‑day review targets going forward.

Commissioners asked for clarity about the number of affected parcels (staff cited ~700 affected parcels and ~500 homes destroyed) and how many applicants have reached planning verification; staff and commissioners encouraged residents to submit applications and flagged that delays also reflect applicant submittal timing. Commissioner comments emphasized the need for a policy that endures beyond the first batch of rebuilds and for close coordination with public works on drainage issues raised in individual public comments.

Provenance: Public comment by Joe Drummond and staff’s rebuild update appear in the Feb. 2 meeting transcript and staff presentation.