City advances aquifer storage planning; test borings and funding outreach next steps

Mountain House City Council · October 22, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Staff reported progress on aquifer storage and recovery planning, including desktop studies, grant outreach and plans to drill two test borings; staff cited preliminary design and drilling estimates (approximately $4.8M design and $5.8M drill per well) and said the next step is test drilling and geophysical characterizations.

City staff provided a quarterly update on aquifer storage and recovery (ASR) planning and early procurement steps.

Staff explained the ASR program seeks to diversify the city's water supply and storage beyond pre-1914 water rights and listed parallel projects (raw-water storage, Wickland cut, Tracy tie-in) being evaluated. Staff said the ASR program will complete desktop studies and then proceed to a test-boring program at two candidate sites (one near the water-quality basin north of Byron Highway and one near the southern tip of a developer parcel) with temporary access agreements under negotiation.

On costs, staff stated planning-level estimates of roughly $4.8 million for design and about $5.8 million to drill (per well) and said the city is considering two to three wells in total. The next immediate steps are issuing an RFP for test-boring contractors, completing the desktop study and performing the field test borings and geophysical logging to characterize aquifer cross-sections.

Staff also reported coordination with grant teams, lobbyists, and federal/state partners and described an early-stage funding pipeline and outreach; the city has spent a small percentage of the awarded project budget to date and expects test drilling to be the near-term capital activity.