Buckner council approves change order after reed-bed contractor finds sandy liner material

Buckner City Council · September 4, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Council approved change order number one for the reed-bed project after staff reported the on-site stockpile was sand rather than clay, requiring hauling clay 12 miles at an estimated extra cost of $40,000 and a check valve addition to prevent pump-station backups.

City staff updated the council on the reed-bed stormwater project and requested approval of a change order after the construction contractor encountered unanticipated site conditions.

Staff said the project team discovered power-line and force-main locations differed from the plans, requiring relocation of pipework and addition of a manhole. When crews poured the lift-station wall, groundwater and wet conditions caused the excavation to fill and crews spent several hours pumping the trench, prompting the installation of a check valve to prevent future backups of solids into the line.

The larger budget impact came when the team began placing the clay liner and determined the on-site stockpile was sandy rather than clay. Staff reported tests showed a nearby farmer’s excavated pond supplied acceptable clay but hauling the clay roughly 12 miles would add an estimated $40,000 in hauling and material cost, with other changes totaling about $14,000. Staff told the council they remained under the original overall project budget but asked permission to proceed to avoid delay.

The council moved to approve change order number one; the motion was seconded and carried by voice vote with no roll-call recorded.

Next steps: staff will authorize the clay haul, complete liner placement and continue project work under the approved change order.