Commissioners and department chiefs reviewed the city The Berlin Police and Fire Commission reviewed the public-safety capital improvement plan for 2026–2030 on Sept. 3, 2025, hearing department estimates that vehicle replacement, body-camera programs and information-technology costs are higher than earlier drafts and may require revised funding assumptions.
Get email alerts on the Capital Improvement Plan topic
No spam. Unsubscribe anytime.
Berlin — The Police and Fire Commission on Sept. 3 reviewed draft capital-improvement-plan (CIP) items for the police and fire departments and heard officials say vehicle and technology costs are higher than earlier estimates, potentially requiring council-level reprioritization.
Police staff told commissioners the version in members
The police presenter said the packet contained an older figure for total uses by project and that the correct total should read $350,000 rather than $345,000. The department noted its current squad vehicles are in the roughly $70,000 range, and that a $35,000 annual set-aside would likely not be sufficient to keep pace with replacement costs in coming years. "If we build a new car in two years, it" said the police chief, adding that realistic planning should account for higher future purchase prices.
The department also described a small-scale body-camera pilot (three cameras on hand) and estimated a continuing program might carry roughly $6,000 per year in ongoing costs. Portable radios are not due for replacement until about 2030, planners said. On conducted-energy devices, staff said existing tasers are past their five-year expected service life and cost about $2,000 apiece; upgrading to manufacturer
The presenter said a potential upgrade path would cost on the order of $40,000 for a department of this size. The department also corrected an IT estimate after noting it paid roughly $11,000 for a server purchased last September and now estimates a future replacement closer to $15,000 in five years.
On an item described in the CIP packet as a "chief squad," the presenter said, "I don" and recommended removing it from immediate consideration, noting both departmental need and anticipated public resistance.
Fire department leaders walked commissioners through their CIP priorities for 2026
For 2026 the department listed $5,000 for station furniture and small replacements. A new engine (Engine 66) is on order with delivery expected in 2027; the packet lists the city's share at about $266,000. The department said it has roughly $100,000 available as a down payment toward replacing its older rescue unit (a 1992 vehicle converted for rescue use) and will consider used options to avoid the full cost of a new ambulance. Longer-term items include a possible chassis-only replacement for Engine 69, upgrades to station kitchen facilities to permit fundraising, a gear dryer replacement, staggered turnout gear replacement and a future command-vehicle replacement that was estimated at about $250,000.
Presenters reiterated that the CIP is an informational planning tool for the city council covering 2026 and that inclusion in the plan does not guarantee funding or a specific implementation year. Commissioners were advised they may forward suggested edits to staff or council for consideration.
Next steps: staff will finalize the CIP draft for council review; commissioners may submit suggested revisions or questions to staff and the council before formal adoption.