Board approves parking change order; contractors to consolidate fencing and add gravel spaces before graduation

Wright City R-II School Board · April 22, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Wright City R-II approved an owner-directed change order to add temporary and long-term parking near the new gym ahead of graduation; administration said contractors will install an ADA ramp, condense fencing, regain about 30 spots and create a gravel lot that could provide up to ~130 additional spaces.

The Wright City R-II Board voted 7–0 to approve an owner-directed change order to expand on-site parking and support graduation logistics as construction proceeds on the new performance gym.

Administration explained the work will be performed by LCS, the contractor already on site, to speed the schedule and reduce contract handoffs. Construction staff reported that foundation and footings are roughly 50% complete and that demolition and removal of fiber cement panels occurred earlier in the project. To ensure accessibility for graduation, the project team said it will install an ADA-compliant ramp with side rails before the ceremony and condense the fenced construction area to recover about 30 parking spaces. A proposed gravel parking area could add roughly 130 additional spots; the plan calls for building the gravel lot to a base specification that would allow future conversion to concrete when funding is available.

Board members raised the timing and completion-date concerns; administrators described the earlier anticipated completion as April but cautioned timelines are 'anticipated' and subject to change. The board approved Change Order Number Two by voice/roll call (recorded as 7–0 in the minutes). Administration said it has requested pricing for permanent paving and will report costs back to the board for future budgeting decisions.

The change-order approval is explicitly intended to address near-term graduation needs while preserving the option to upgrade the gravel lot later if bond capacity or other funding is available.