Engineers report: Kingman Road Park change order, 2026 road program bids and Twin Oaks CAD-file dispute
Summary
Engineer Andrew Pals recommended a $2,820 change order and a $28,442 pay application for Kingman Road Park, reviewed 2026 road-program bids with AFD Damon Company as low bidder, and reported a contractor request for a $2,200 change order and 30‑day extension for Twin Oaks because CAD files were not provided.
Get email alerts on the Public Works topic
No spam. Unsubscribe anytime.
The Upper Chichester Township caucus heard multiple public-works updates from engineer Andrew Pals on May 12, including a small change order request for a park improvement, pay applications, low bids for the 2026 road program, and a dispute over CAD-file ownership that is delaying the Twin Oaks entrance work.
Kingman Road Park: Pals said change order number nine is needed to allow the pour‑in‑place contractor to feather and adjust stone on the new surface to avoid ponding; he stated the cost would be $2,820 and recommended a pay application of $28,442 covering sign work and the new court surface. "That's going to be a cost of $2,820," Pals said, and recommended the payment for the contractor's certified work.
Streetscape and road program bids: The Johnson Avenue streetscape pay application presented covers additional curb, sidewalk and roadway widening for $39,419.10. Bids opened May 6 for the township’s 2026 road program; Pals said AFD Damon Company was the low bidder on the base bid at $53,584. Four alternates were submitted: Creek Parkway $30,085; Chelsea Parkway $38,415; Arlington Road $16,645; Kingsman Road $29,318. Pals recommended awarding the base bid and the Chelsea Parkway alternate.
Twin Oaks entrance: the contractor requested a $2,200 change order and a 30‑day extension, saying it could not access CAD files from the previous engineer and its surveyor could not complete layout without them. Pals said he has asked the county to review whether the change order is appropriate and recommended paying the $2,200 if the county approves to avoid further delay. "The previous engineer is just not releasing those files," he said, and contractors reported they had expected the electronic CAD deliverables when they bid the job.
What comes next: county approval is pending for the Twin Oaks change order; pay applications and recommended awards for the 2026 road program will move to the business meeting agenda for formal action. The engineer said Kingsman Road project is approaching substantial completion and that remaining work is primarily punch‑list items.
No formal decisions on awarding contracts or approving the Twin Oaks change order were finalized in caucus; those actions are expected on the business meeting agenda.