Board approves LTFM plan revision and preliminary bond resolutions to fund HVAC and accessibility repairs

Austin Public School District Board of Education · March 9, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The board adopted a revised fiscal-year 2027 long-term facilities maintenance (LTFM) 10-year plan and approved preliminary resolutions to issue bonds (general-obligation facility maintenance, capital facilities and tax-abatement bonds) to fund indoor air-quality projects and accessibility repairs; the presentation estimated a tax example of $89/year on a $200,000 home and set a public hearing for April 13 for abatement bonds.

The Austin Public School District board approved a revised fiscal-year 2027 long-term facilities maintenance (LTFM) 10-year plan and voted to adopt a preliminary resolution to pursue several bond financing components to fund maintenance and health-and-safety projects.

Financial advisor Michael Hart (PTMA) outlined three financing components presented to the board: general-obligation facility maintenance bonds capped in the presentation at $19.2 million (this ceiling includes estimated financing costs), capital facilities bonds for targeted bathroom and electrical work at an identified building, and tax-abatement bonds for parking-lot repairs (amount not to exceed $140,000). The presentation emphasized that projects are limited to maintenance and health-and-safety work, not new construction or expansion.

Hart presented a sample tax impact under a 20-year debt-service structure: approximately $89 per year for a $200,000 home, with most of the impact attributable to indoor-air-quality projects. He also reviewed timeline steps: state submissions for the revised LTFM and capital-facilities plans in March, a public hearing on tax-abatement bonds scheduled for the board’s April 13 meeting, and design and bid work to enable construction work beginning in summer 2027. Hart noted the district had roughly $3 million in assigned funds that will be used to retire an existing bond on the event center and reissue capital-facilities capacity to increase flexibility for the projects.

After discussion, the board approved the LTFM plan revision by voice vote and passed the preliminary resolution to issue the listed bonds (motion on the preliminary resolution moved by CC and seconded by Dan). The transcript does not include individual vote tallies.

Next steps include filing required notices and the scheduled public hearing on April 13 for the abatement bonds; staff expects to return with more detailed financing steps before bond sale and construction.