At its Aug. 13 meeting the Board of Aldermen approved grant-acceptance resolutions for recreation trails and Gadison Park, approved $6.7M site proposal for 35 North Main, awarded an Olsen Drive remediation contract, and selected a planner for the Opera House.
Get email alerts on the Votes Roundup topic
No spam. Unsubscribe anytime.
The Ansonia Board of Aldermen used its Aug. 13 meeting to approve several formal items required to move city projects forward.
Key actions taken by voice vote:
- Acceptance of state/federal funds for the Ansonia Recreation Trails project (resolution approved).
- Acceptance of federal funds (passed through OPM) for rehabilitation at Gadison Park; staff described planned removal and replacement of playground equipment, fencing, lighting, benches, walkways and public-art space within budget constraints.
- Approval of a $6.7 million funding proposal for 35 North Main Street to support remediation, demolition and site preparation connected to downtown redevelopment.
- Award of the environmental-remediation contract for the Olsen Drive field site to Eniro Consulting to implement a $3.8 million cleanup grant and begin soil removal and on/off-site handling.
- Selection of Patrick Quinn & Associates to perform a planning and survey study for the Ansonia Opera House following an earlier feasibility study; renderings and a public presentation were promised for early fall.
Officials said the grants are largely reimbursable and that some work will begin only when short-term financing or grant-anticipation notes are in place. The board recorded each motion and approved them in sequence during the meeting; staff will return with implementation schedules and procurement steps.