Commissioners approve ARPA-funded sewer change order and multiple progress payments for Ames and Harden projects
Summary
The court approved a $131,689 change order for CA Construction and several progress payments to CNA/CANA/King Solutions for ARPA-funded sewer improvements in Ames and Harden, with staff confirming ARPA as the funding source.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
At its May 26 meeting Liberty County's commissioners approved a change order and several progress payments tied to ARPA-funded sanitary-sewer improvements for Ames and Harden.
County staff presented Change Order No. 4 for CA Construction LLC in the amount of $131,689 for the ARPA sewer improvements for the city of Ames; the court approved the change order, with staff noting required backups were attached to the packet.
The court also approved progress payment No. 8 to CNA Construction LLC for $61,236.85 and additional progress payments and estimate payments listed in the meeting packet (including CANA Construction and King Solutions LLC for Harden sanitary sewer rehabilitation). Staff repeatedly confirmed these were ARPA-funded projects during the motions.
Each payment and the change order were approved by voice motion and second; staff will continue to process contractor invoices and maintain documentation in the project files.