Council rejects high bids for labor-exchange building and directs lower-cost redesign, explores triangle parcel alternative
Summary
After staff presented $1.5 million construction bids for a small labor-exchange facility and noted a roughly $97,000 shortfall against approved funding, council voted to reject the bids and directed staff to redesign lower-cost alternatives (cap on new general-fund exposure $250,000) and to evaluate relocating the project to the Triangle parcel or using temporary structures.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
Councilors moved to reject the high construction bids for a proposed Malibu Community Labor Exchange facility and directed staff to return with lower-cost options.
Staff presented seven bid results and identified the lowest responsive bid at approximately $1.51 million for construction, with a total project estimate near $1.98 million once design and contingencies were included. Staff told the council the project currently uses a mix of a community development block grant (CDBG) allocation (~$140,482) and a previously approved general-fund allocation; if the city cancels the project this fiscal year it may need to return used CDBG funds unless an extension is negotiated with the grant manager.
A local contractor who spoke during public comment urged value engineering and said the cost seemed high for the proposed scope: “we're talking about a 700 square foot box with a couple of doors and a toilet,” the contractor said, and asked staff to pursue cost reductions and possible schedule extensions for the CDBG award. Council members voiced concern about spending more than a modest additional general-fund amount on the project and asked staff to examine cheaper prefab or repurposed modular options. Several council members asked staff to evaluate whether a smaller, lower-cost solution could be delivered on the site or whether temporary facilities or the Triangle parcel might be better short-term options.
Council direction and limits: The council voted to reject the current bids and asked staff to redesign and re-bid lower-cost alternatives, with a cap on new general-fund exposure of $250,000 beyond already-allocated funds; staff also was directed to explore using the Triangle parcel as an alternate location or temporary parking/structure solution. Staff said it will also pursue a possible CDBG extension and report back with value-engineered alternatives, precise cost estimates and any funding gaps.
Why it matters: The Labor Exchange has served as a place for local labor matching and services; council members said they want to preserve the function but not at the cost of a large capital commitment when less expensive modular or temporary options may suffice. Council emphasized that any return to the agenda must include a realistic, lower-cost option and transparent funding sources before any award of construction funds.
Next steps: Staff will pursue value-engineering, seek a CDBG timing extension if possible, and return with specific lower-cost alternatives, revised budgets and an evaluation of the Triangle parcel as an alternate location.