Council moves forward on emergency repairs to historic train depot, requests more insurance detail

Pecos City Council · May 29, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Council approved staff to proceed with emergency coordination on the city‑owned train depot reconstruction using the city’s insurance carrier and recommended contractor, while requesting further detail on cost, historic preservation, and the reimbursement process before full authorization of the insurance allowance.

City staff asked the council on May 28 to authorize emergency repairs and reconstruction of the city‑owned train depot after damage was confirmed to constitute a public‑safety concern and public nuisance. The resolution would authorize the city manager to negotiate and execute contracts up to $1,018,085 in order to access the city’s insurance coverage and to use TML IRP’s recommended contractor, Calvary Construction and Restoration.

Heather Ramirez summarized the request and the insurance context, saying the contractor provided a quote of about $831,000 but that additional engineering and code‑upgrade costs could raise the total. "The amount will be 1,018,085," Ramirez said, describing the upper limit staff would seek to access through the insurance allowance. Staff also reported that TML had identified the depot as city‑owned (land leased from Union Pacific) and that TML has already advanced $336,000 to begin work.

Council members asked whether demolition and replacement (versus repair to historic form) might yield more funds for other downtown projects and whether HOT tax funds would be used. Staff said the insurance process provides initial funds and that final reimbursement depends on the insurance claim and possible legal recovery; staff emphasized the likelihood of only partial recovery if the building were demolished.

Council voted to move the item forward and directed staff to return at the next meeting with additional information from TML and the city’s adjusters to clarify what would be recoverable and what the city would be asked to cover. No final demolition or reconstruction contract was executed tonight; council asked for two weeks for staff to report back with clearer cost‑recovery options and historic‑preservation implications.