Planning board grants one-year extension for Enclave at Hyde Park after residents raise sewer and wetland concerns
Summary
On July 16 the Hyde Park Planning Board approved a retroactive one-year extension to complete the Enclave at Hyde Park subdivision, after residents questioned wastewater discharge and local flooding. The board noted outstanding bond issues and agreed to withhold certificates of occupancy until county road work is completed.
Get email alerts on the Enclave Hyde Park topic
No spam. Unsubscribe anytime.
The Hyde Park Planning Board on July 16 voted to grant a retroactive one-year extension for the Enclave at Hyde Park, moving the deadline to complete substantial construction to June 11, 2026, under Resolution 16-49Q. The resolution was presented to the board and carried on a voice vote.
The extension applies to a long-running subdivision on Cream Street at Long Branch Road that predates current zoning. Pete (consultant) told the board the developer submitted two new bonds — a performance bond for road completion and a five-year maintenance bond for the wastewater treatment plant — and that the town board accepted the bonds on April 14, though minor issues remain to be resolved. Pete said that once bond issues are corrected the developer may obtain building permits, but the town will withhold certificates of occupancy until the county is satisfied with road reconstruction.
The project was originally approved as a single-family subdivision in 2007 and modified in 2018; the modified plan consolidated lots and created an approximately 46-acre open-space water-supply lot. Victoria said the amendment reduced net buildable lots and concentrated development on one side of the parcel, allowing smaller lots (about 0.3–0.6 acre) where community water and sewer are provided.
During public comment, resident Frank Cole (243 Cream Street) asked whether the wastewater treatment plant and water system are authorized and operational. Pete replied, “The sewer plant was built. It was completed within the last year or so and ... it was inspected by both the project engineer [and] the county health department. So, it has been issued an authorization to operate.” He reiterated that the system had been reviewed by the relevant health authorities.
Another resident, Rich Green (12 Henry Street), raised concerns that treated effluent would discharge to an intermittent stream he described as wetland and noted standing water and beaver dams upstream. Green asked, “It's gonna dump gray water in there?” Pete and other staff responded that the discharge is treated and that the development includes stormwater retention ponds; they also said the DEC and county health department reviewed and approved the system. Board staff acknowledged localized drainage and beaver-related flooding issues and noted the highway department had performed clearing at times.
Board members and staff emphasized that the 46-acre open-space lot is preserved under the approved subdivision arrangement and cannot be developed later, a factor that enabled the density consolidation on the developed portion of the parcel.
Tuttle read Resolution 16-49Q, which grants the retroactive one-year extension to June 11, 2026. After the voice vote carried, members observed this is the project's seventh extension since 2019 and cautioned the developer may return for another extension if work is not completed.
The board’s action extends the deadline for substantial completion but does not change prior approvals or override county conditions tied to road reconstruction and certificates of occupancy.