Council approves $65,357 change order to extend Eagle Crest storm pipe; one abstention

City of Broken Bow City Council · July 9, 2024
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The council approved Change Order 1 for the Eagle Crest Subdivision on July 9: a $65,357 extension of storm piping (350 feet total) to address drainage and allow future connections; Councilmember Chris Myers abstained.

The City of Broken Bow City Council approved Change Order 1 for the Eagle Crest Subdivision project at its July 9 meeting. JEO representative Ryan Kavan explained the change order: extending pipe 350 feet from the originally proposed terminus (75 feet of 24-inch pipe and 275 feet of 18-inch pipe), filling the ditch with pipe and soil, installing inlets, and extending the work across Hillcrest Drive to allow the city to tap the pipe in the future for a storm sewer along Hillcrest Drive.

The motion to approve the change order for $65,357.00 was made by Councilmember Russ Smith and seconded by Councilmember Paul Holland. The roll call vote was 3–0 with Councilmember Chris Myers recorded as abstaining. Mayor Sonnichsen noted the project cost came in under initial expectations and that the change order addresses future drainage needs.